Best Pratice Detail

Legend: Best Practices: 1 Capabilities: 3 Outcomes: 8 Prerequisites: 5

1080 - Project Schedule Development Process Standardization

Project Schedule Development Process standards are established. PROJECT, STANDARDIZE

1080.010 - Process Management Governing Body

The organization enables Project Schedule Development process improvements by authorizing the appropriate governing bodies to make critical decisions on process improvement goals and plans. IPECC: Planning PROJECT, STANDARDIZE

1080.010.10 - Active Process Governing Body

Process-oriented governing bodies have been established, and the appropriate people have been assigned to them. They meet on a regular schedule to discuss process management issues and suggestions for improvements. KPI Name: Process Governing Body

1000.010 - Established Standardization Policies

The organization has policies explaining which organizational project management processes must be standardized. IPECC: Executing PROJECT, PROGRAM, PORTFOLIO, STANDARDIZE, MEASURE, CONTROL, IMPROVE

1000.010.10 - Standardization Policies

Standardization Policies are documented and communicated to all stakeholders. KPI Name: Documented Standardization Policies

1080.020 - Project Schedule Development Process Development

The organization assembles, develops, purchases, or otherwise acquires a Project Schedule Development process. IPECC: Planning PROJECT, STANDARDIZE

1080.020.10 - Documented Project Schedule Development Process

A Project Schedule Development Process is documented and communicated to all necessary stakeholders. KPI Name: A Documented Project Schedule Development Process Exists

1060.030 - Standardize Project Activity Sequencing Processes

The organization standardizes the Project Activity Sequencing process. IPECC: Planning PROJECT, STANDARDIZE

1060.030.10 - Standardized Project Activity Sequencing Process

Work methods for the Project Activity Sequencing Process are implemented consistently, producing project network diagrams and activity list updates. KPI Name: Evidence of Consistent Implementation

1070.030 - Standardize Project Activity Duration Estimating Processes

The organization standardizes the Project Activity Duration Estimating process. IPECC: Planning PROJECT, STANDARDIZE

1070.030.10 - Standardized Project Activity Duration Estimating Process

Work methods for the Project Activity Duration Estimating Process are implemented consistently, producing activity duration estimates, basis of estimates, and activity list updates. KPI Name: Evidence of Consistent Implementation

1090.030 - Standardize Project Resource Planning Processes

The organization standardizes the Project Resource Planning process. IPECC: Planning PROJECT, STANDARDIZE

1090.030.10 - Standardized Project Resource Planning Process

Work methods for the Project Resource Planning Process are implemented consistently, producing resource requirements. KPI Name: Evidence of Consistent Implementation

1160.030 - Standardize Project Communications Planning Processes

The organization standardizes the Project Communications Planning process. IPECC: Planning PROJECT, STANDARDIZE

1160.030.10 - Standardized Project Communications Planning Process

Work methods for the Project Communications Planning Process are implemented consistently, producing Communications Management Plans. KPI Name: Evidence of Consistent Implementation

1080.030 - Standardize Project Schedule Development Processes

The organization standardizes the Project Schedule Development process. IPECC: Planning PROJECT, STANDARDIZE

1080.030.10 - Standardized Project Schedule Development Process

Work methods for the Project Schedule Development Process are implemented consistently, producing project schedules, supporting detail, Schedule Management plans, and resource requirement updates. KPI Name: Evidence of Consistent Implementation